Do you know the key points of mold test?

Introduction: The mold is the core pillar of the packaging material. The quality of the mold determines the quality of the packaging material. Before the injection molding of a new mold or when the machine is replaced with other molds, the trial mold is an indispensable part. This article is edited by shanghai rainbow package. , Share a few key points of injection mold trial, the content is for the purchase of Youpin supply chain for friends’ reference:

Tryout

When receiving a new mold for proofing and testing, I always eager to try a result earlier and hope the process goes smoothly so as not to waste man-hours and cause trouble.

Mould

However, two points must be reminded here: First, mold designers and manufacturing technicians sometimes make mistakes. If they are not vigilant during mold trial, small mistakes may cause big damage. Second, the result of mold trial is to ensure smooth production in the future. If reasonable steps and proper records are not followed during the mold trial process, the smooth progress of mass production cannot be guaranteed. We emphasize that if the mold is used smoothly, the profit recovery will be increased quickly, otherwise the cost loss caused will be more than the cost of the mold itself.

01 Precautions before mold trial
Understand the relevant information of the mold:

It is best to obtain the design drawing of the mold, analyze it in detail, and ask a mold technician to participate in the trial work.

微信图片_20211018102522

 

First check the mechanical coordination action on the workbench:

Pay attention to whether there are scratches, missing parts, looseness, etc., whether the movement of the mold toward the slide plate is correct, whether there is any leakage in the water channel and air pipe joints, and if there are restrictions on the mold opening, it should also be marked on the mold. If the above actions can be done before hanging the mold, it is possible to avoid the waste of man-hours when the problem is found when hanging the mold and then the mold is disassembled.

When it is determined that each part of the mold moves properly, it is necessary to select a suitable test mold injection machine. When selecting, pay attention to:

(a) Injection capacity

(b) The width of the guide rod

(c) Maximum departure

(d) Whether the accessories are complete, etc.

微信图片_20211018102656

 

After everything is confirmed that there is no problem, the next step is to hang the mold. When hanging, be careful not to remove all the clamping templates and before opening the mold, so as to prevent the clamping template from loosening or breaking and causing the mold to fall.

After the mold is installed, carefully check the mechanical movements of each part of the mold, such as the movement of the sliding plate, thimble, withdrawal structure, and limit switch. And pay attention to whether the injection nozzle and the feed port are aligned. The next step is to pay attention to the mold clamping action. At this time, the mold closing pressure should be lowered. In manual and low-speed mold clamping actions, pay attention to see and listen for any unsmooth movements and abnormal noises.

Increase mold temperature:

According to the properties of the raw materials used in the finished product and the size of the mold, an appropriate mold temperature control machine is selected to increase the temperature of the mold to the temperature required for production.

After the mold temperature is increased, the movement of each part must be checked again, because the steel may cause a jam phenomenon after thermal expansion, so pay attention to the sliding of each part to avoid strain and vibration.

If the experiment plan rule is not implemented in the factory, we suggest that when adjusting the test conditions, only one condition can be adjusted at a time, in order to distinguish the impact of a single condition change on the finished product.

Depending on the raw materials, the raw materials used should be baked appropriately.

Try to use the same raw materials as much as possible for mass production in the future.

Do not try the mold completely with the inferior material. If there is a color requirement, you can arrange the color test together.

Problems such as internal stress often affect the secondary processing. After the mold is tested, the finished product should be stabilized and the secondary processing should be performed. After the mold is closed at a slow speed, adjust the mold closing pressure and perform several actions to check whether there is mold clamping pressure. Uneven phenomenon, so as to avoid burrs and mold deformation in the finished product.

After checking the above steps, lower the mold closing speed and pressure, and set the safety hook and ejection stroke, and then adjust the normal mold closing and closing speed. If the maximum stroke limit switch is involved, the mold opening stroke should be adjusted slightly shorter, and the high-speed mold opening action should be cut before the maximum stroke of the mold opening. This is because the high-speed movement stroke is longer than the low-speed stroke in the entire mold opening stroke during mold loading. On the plastic machine, the mechanical ejector rod must also be adjusted to act after the full-speed mold opening action to prevent the ejector plate or the peeling plate from being deformed by force.

Please check the following items again before making the first mold injection:

(a) Whether the feeding stroke is too long or insufficient.

(b) Whether the pressure is too high or too low.

(c) Whether the filling speed is too fast or too slow.

(d) Whether the processing cycle is too long or too short.

In order to prevent the finished product from short shot, fracture, deformation, burrs and even damage to the mold.

If the processing cycle is too short, the thimble will penetrate the finished product or squeeze the finished product by peeling the ring. This type of situation may cost you two or three hours to take out the finished product.

If the processing cycle is too long, the weak parts of the mold core may be broken due to the shrinkage of the rubber material. Of course, you can’t predict all the problems that may occur in the trial mold process, but full consideration and timely measures can help you avoid serious and expensive losses.

02 The main steps of tryout
In order to avoid unnecessary waste of time and troubles during mass production, it is indeed necessary to pay patience to adjust and control various processing conditions, find the best temperature and pressure conditions, and formulate standard test procedures, which can be used in Establish daily working methods.

new mould

1) Check whether the plastic material in the barrel is correct, and whether it has been baked in accordance with the regulations. (If different raw materials are used for trial and production, different results may be obtained).

2) The material pipe must be cleaned thoroughly to prevent the inferior glue or miscellaneous materials from being injected into the mold, because the inferior glue and miscellaneous materials may jam the mold. Test whether the temperature of the barrel and the temperature of the mold are suitable for the raw materials to be processed.

3) Adjust the pressure and injection volume to produce a finished product with a satisfactory appearance, but do not run off the burrs, especially when some mold cavity products are not completely solidified. Think about it before adjusting various control conditions, because mold filling A slight change in the rate may cause a large change in the filling of the mold.

4) Wait patiently until the conditions of the machine and mold stabilize, even for medium-sized machines, it may take more than 30 minutes. You can use this time to view possible problems with the finished product.

5) The advancing time of the screw should not be shorter than the solidification time of the gate plastic, otherwise the weight of the finished product will be reduced and the performance of the finished product will be impaired. And when the mold is heated, the screw advance time needs to be prolonged in order to compact the finished product.

6) Reasonably adjust to reduce the total processing cycle.

7) Run the newly adjusted conditions for at least 30 minutes to stabilize, and then continuously produce at least a dozen full mold samples, mark the date and quantity on the container, and place them according to the mold cavity to test the stability of the actual operation And derive reasonable control tolerances. (Particularly valuable for multi-cavity molds).

8) Measure and record the important dimensions of continuous samples (we should wait for the samples to cool to room temperature before measuring).

Comparing the measured size of each mold sample, you should pay attention to:

(a) Whether the size is stable.

(b) Are there certain dimensions that have a tendency to increase or decrease indicating that the machining conditions are still changing, such as poor temperature control or oil pressure control.

(c) Whether the size change is within the tolerance range.

If the size of the finished product does not change and the processing conditions are normal, it is necessary to observe whether the quality of the finished product of each cavity is acceptable and its size can be within the allowable tolerance. Note down the number of cavities that are continuous or larger or smaller than the average to check whether the size of the mold is correct. Record and analyze the data as the need to modify the mold and production conditions, and as a reference for future mass production.

03 Problems that should be paid attention to during mold trial
1) Make the processing operation time longer to stabilize the melt temperature and hydraulic oil temperature.

2) Adjust the machine conditions according to the size of all finished products that are too large or too small. If the shrinkage rate is too large and the finished product appears to be insufficient to shoot, you can also increase the gate size by referring to it.

3) The size of each cavity is too large or too small to be corrected. If the size of the cavity and the door is still correct, then try to modify the machine conditions, such as the filling rate, the temperature of the mold and the pressure of each part, and check some molds. Whether the cavity fills the mold slowly.

4) According to the matching situation of the finished products of the mold cavity or the displacement of the mold core, it will be modified separately. It is also allowed to try to adjust the filling rate and mold temperature to improve its uniformity.

5) Check and modify the faults of the injection machine, such as the oil pump, oil valve, temperature controller, etc., will cause changes in the processing conditions, even the perfect mold can not play a good work efficiency on the poorly maintained machine.

After reviewing all the recorded values, keep a set of samples for proofreading to compare whether the corrected samples have improved.

04 Important matters
Properly keep all the records of sample inspection during the mold trial process, including various pressures during the processing cycle, melt and mold temperature, barrel temperature, injection action time, screw feeding period, etc. In short, you should save everything that will help in the future It can be used to successfully establish the data of the same processing conditions in order to obtain products that meet the quality standards.

At present, the mold temperature is often neglected during mold trial in the factory, and the mold temperature is the most difficult to grasp during short-term mold trial and future mass production. Incorrect mold temperature can affect the size, brightness, shrinkage, flow pattern and lack of material of the sample. , If the mold temperature controller is not used to control the future mass production, difficulties may arise.

Shanghai Rainbow Industrial Co., Ltd is the manufacturer, Shanghai rainbow package Provide one-stop cosmetic packaging.If you like our products, you can contact us,
Website: www.rainbow-pkg.com
Email: Bobby@rainbow-pkg.com
WhatsApp: +008613818823743


Post time: Oct-18-2021
Sign Up